Napa County Library Lighting Retrofit Project PW 13-32

Status: Complete
Contact: Zandra Massari
Publish Date: 2013-05-02


The work generally consists of, but is not limited to all labor and materials for:

Removal and disposal of certain portions of existing light fixture and controls. installation of new energy efficient retrofit lights, work also includes validation of existing light levels and post retrofit light levels.  Contractor shall provide all labor and materials to have a complete and operable system whether shown or not shown.  All work shall meet all applicable codes.  All work under this contract shall be done during evenings and weekends.  AED Electric of Manteca, CA was low bidder with the bid amount of $52,961.33.  The project is now complete.