Rutherford Dust Restoration Project, Reaches 5,6,7,9

WE ARE NAPA COUNTY

Public WorksConstruction and Design Engineering

Construction Design

Rutherford Dust Restoration Project, Reaches 5,6,7,9 PW 14-09

Status: Complete
Contact: John Vicencio
Publish Date: 2013-10-15


Neighbors to the Rutherford Reach of the Napa River have voluntarily put together a restoration project that will include 5 miles of new riparian habitat and relocation of berms. These are the remaining 4 Reaches for this project and are anticipated for construction in the summers of 2014, 2015.

The Engineer's estimate for construction is $2,084,280. The bid opening was on May 22, 2014 at 3:30 pm per Addendum 2, no bids were accepted after 3:30 pm. The contract was awarded to Hanford ARC on June 17, 2014 for their low Total Base Bid of $1,769,986.


Return to Summary