Five Dual-Completion Monitoring Wells, PW 14-31

WE ARE NAPA COUNTY

Five Dual-Completion Monitoring Wells, PW 14-31

Status: Evaluation/Review
Contact: Patrick Lowe
Publish Date: 2014-06-16


The work generally consists of, but is not limited to the construction of five dual-completion monitoring wells at five different sites in Napa County located between Napa and St. Helena.

The Engineer's estimate for this project is $51,000.  Contractor shall possess a Class C-57 license at the time of the contract award.

One mandatory pre-bid meeting was scheduled for Wednesday, June 25, 2014 at 9 a.m.  All questions were to be received by July 7, 2014 at 12 p.m.  The bid opening was on July 17, 2014 at 3:30 p.m.  No bids were accepted after 3:30 p.m.

View, print, or download Notice to ContractorView, print, or download Plans and SpecificationsView, print, or download Sign in Sheet 04-25-14View, print, or download Addendum #1.

Currently bids are being evaluated.

ContractorTotal Base Bid
Clear Heart Drilling - Santa Rosa, CA

$77,250

Penecore Drilling - Woodland, CA

$99,500

 


Return to Summary