Oakville to Oak Knoll Reach - Group C Sites 11, 12, adn 13, PW 17-14

WE ARE NAPA COUNTY

Oakville to Oak Knoll Reach - Group C Sites 11, 12, and 13, PW 17-14

Status: Construction
Contact: Andrew Butler
Publish Date: 2017-05-11


The project is located on the East bank of the Napa River starting at the Yountville Cross Road bridge and extending approximately 3,000 ft. to the South. The work will include but is not limited to demolition of abandoned vineyard and associated infrastructure, grading, excavation and off haul of soil, construction of biotechnical stabilization structures, construction of habitat features, and deployment of erosion controls measures. Print, view, or download Siteworks sublist. Print, view, or download Team Ghilotti sublist. Print, view, or download Hanford ARC. Print, view, or download Intent to Award. The project was awarded on Tuesday, July 11, 2017 by the Board of Supervisors.

Contractor                                 Base Bid        Add Alt#1       Add Alt#2      Add Alt#3A      Add Alt #3B     
Siteworks - Lafayette$2,564,597.76$258,331.06$298,042.64$180,772.02$187,809.57
Team Ghilotti - Petaluma$3,357,506.00$544,379.00$618,863.25$377,408.00$387,851.75
Hanford ARC - Sonoma$4,047,625.00$490,737.00$348,702.00$255,317.00$377,664.00

Return to Summary