Water Tank Replacement LBRID

LB 15-02R

Overview

The project includes the following: furnishing and installation of one (1) new 180,000 gallon bolted steel water storage tank and one (1) new 85,000 gallon bolted steel water tank.

Contract

The project was awarded by the LBRID Board on January 10, 2017 to RSH Construction of Hemet, CA.

Bids

Contractor Location Total Base Bid
RSH Construction Hemet, CA $1,302,250.00
TNT Industrial Contractors Sacramento, CA $1,430,046.00
Holitna Construction Suisun City, CA $1,487,750.00
Hess Construction American Canyon, CA $1,611,104.00
Coleman Construction Upper Lake, CA $1,727,301.00