Construction

Runway Resurfacing Project

Currently Phase 3 of 6.

For construction updates, please email us to be added to the Construction Update address list.

The details of the construction phasing plan can be found in the Airport Construction Phases Poster (PDF)

Phase 3 Operational Impacts

*Check NOTAMS for up-to-date information* 

PHASE 3 of 6

thumbnail image of map for phase 3 of Napa County Airport’s runway rehabilitation project  Opens in new window(Click image above for larger view of Phase 3 map)

Work Schedule:
April 15th, 2019 to June 22nd, 2019

Operational Runway:
RWY 18R/36L (4,146 feet)
RWY 18L/36R (2,500 feet)

Closed Runway:
RWY 6/24

Closed Taxiways:
TWY H from RWY 18L/36R to RWY 6/24
TWY C from RWY 18R/36L to RWY 6/24
TWY B  

All NAVAIDS will be turned off with the exception of the localizer for RWY 36L and the PAPI for 18R.

*Check NOTAMS for up-to-date information*

WORK COMPLETED and 2 WEEK LOOK AHEAD