Construction

Runway Resurfacing Project

Currently Phase 5 of 6.

For construction updates, please email us to be added to the Construction Update address list.

The details of the construction phasing plan can be found in the Airport Construction Phases Poster (PDF)

Phase 5 Operational Impacts

*Check NOTAMS for up-to-date information* 

PHASE 5 of 6

Phase 5

(Click image above for larger view of Phase 5 map)

Work Schedule:

July 17th, 2019 to September 25th, 2019

Operational Runway:

  • RWY 6/24 (5,009 feet) Back-Taxi Required
  • RWY 18L/36R (2,500 feet)

Closed Runway:

  • RWY 18R/36L

Closed Taxiways:

  • TWY A and TWY K from TWY F to RWY 18R/36L
  • TWY E between RWY 18R/36L and 18L/36R
  • TWY F between RWY 18R/36L and 18L/36R

*Check NOTAMS for up-to-date information*

WORK COMPLETED and 2 WEEK LOOK AHEAD