Silverado Trail Overlay, Phase I&J, Yountville Cross Rd to Skellenger, RDS 18-11

Overview

  • Status: Awarded
  • Contact: Sonja El-Wakil
  • Publish Date: February 22, 2019

Project Scope

Silverado Trail Overlay, Phase I & J, Yountville Cross Road (Mile Post 07.70) to Skellenger Lane (Mile Post 11.10) will install new hot mix asphalt surfacing on Silverado Trail between the intersections of Skellenger Lane and Yountville Cross Road to improve and maintain the road surfacing. 

Contractor shall possess a Class A or C-12 License at the time of contract award.  The Engineers Construction Estimate for this project is $1,330,000.  The project was awarded by the Board of Supervisors on May 7, 2019 to Martin Brothers Construction of Sacramento, CA.  Sublists have been posted.

Contractor Location Base Bid Add Alt#1 Total & Add Alt#1
Martin Brothers Sacramento, CA    $964,268.25 $110,731.75 $1,075,000.00
Granite Construction Ukiah, CA    $973,773.54 $143,652.00 $1,117,425.54
Ghilotti Brothers San Rafael, CA $1,007,553.54 $124,498.40 $1,132,051.94
Team Ghilotti Petaluma, CA $1,362,667.89 $155,623.00 $1,518,290.89