Ridgecrest Dr. MPM 0.4, RDS 18-22

2017 Storm Damage Repair - Grade Beam Wall

FEMA PA-09-CA-4301 PW-01061, NANCC10

Overview

Project Scope

Slope failure from the 2017 storm events have damaged approximately 200 feet of roadway on Ridgecrest Drive (Post Mile 0.40). The damaged area is judged to be an immediate threat to the roadway as it may accelerate with additional rainfall.

Contract

Contractor shall possess a Class "A" License at the time of contract award.  It is anticipated that the project will be built in May 2019 and finish construction in July 2019.

Bid Documents

The Bid Documents are available, for a fee of ten ($10) per CD, which fee is not refundable.  The lowest 3 bidders sublists have been posted.  The Notice of Intent has been posted.  The project was awarded by the Board of Supervisors on April 9, 2019 to Valentine Corporation of San Rafael, CA for their low base bid of $489,369.

Bids

Contractor Location Total Base Bid
Valentine Corp San Rafael, CA $489,369.00
Team Ghilotti Petaluma, CA $531,647.50
McCullough Construction Arcata, CA $535,069.23
Granite Construction Santa Rosa, CA $538,186.20
Rege Construction Cloverdale, CA $556,245.00
Hillside Drilling Point Richmond, CA $608,369.00
Syblon Reid Folsom, CA $609,000.00
Gordon M. Ball Alamo, CA $620,160.00
Northern Pacific Napa, CA $686,060.00