Oakville to Oak Knoll Reach - Group B, Sites 15,17,18,19,20, PW 19-16

Overview

Status:  Awarded
Contact: Andrew Butler
Publish Date: April 8, 2019

Project Scope

The project is located on the East and West banks of the Napa River in a stretch located between Yountville Cross Road and Oakville Cross Road in Napa County. The work will consist of demolition, grading, excavation and off haul of soil, construction of biotechnical stabilization structures, construction of habitat features, and deployment of erosion control measures.

Contract

A Class A license is required for this project.  The project was awarded by the Board of Supervisors on May 21, 2019 to Siteworks Construction.

Bids

Contractor Location Total Base Bid Add Alt #1
Siteworks Construction Lafayette, CA $1,787,075.69 $478,442.87
McCullough Construction Arcata, CA $1,795,481.30 $476,220.07
Granite Construction San Jose, CA $2,507,433.00 $716,030.00
Team Ghilotti Petaluma, CA $2,755,696.73 $783,528.41
Suulutaaq Inc. Suisun City, CA $2,757,856.00 $638,940.00