Construction Work Completed and 2 Week Look Ahead

PHASE 1 of 6: Completed

Linked image of map for phase 1 of Napa County Airport’s runway rehabilitation project  Opens in new window

(Click image above for larger view of Phase 1 map)

Work Done

  • Installation of sub drain pipes adjacent to both side of 18R/36L
  • Repaired a failing section of asphalt on Taxiway K
  • Repaired 4 buckling concrete slabs on 18R/36L

PHASE 2 of 6: Completed

thumbnail image of map for phase 2 of Napa County Airport’s runway rehabilitation project  Opens in new window

(Click image above for larger view of Phase 2 map)

Work Done

  • Striping/marking removal of Runway 18R/36L
  • Relocation of 36L threshold for the temporary shortening of runway to 4,146 feet
  • FAA Flight check of Runway 18R/36L on April 12th
  • Night closure on April 12th, included night work to prepare runway 18R/36L for the temporary shortening
  • Opened 18R/36L in its shortened condition and closed runway 6/24 on April 15th

PHASE 3 of 6: In Progress  

Linked image of map for phase 3 of Napa County Airport’s runway rehabilitation project  Opens in new window

(Click image above for larger view of Phase 3 map)

2 Week Look Ahead

  • Build construction access road to approach end of runway 24
  • Excavate portions of runway 6/24
  • Begin cracking the concrete of portions of runway 6/24
  • Seat sections of cracked concrete following positive test results