NBRID Sewer Lift Station 2 Pump Replacement Project, NB 19-05

NB 19-05

Overview

Project Scope

The location of the work is entirely within the Napa Berryessa Resort Improvement District (District).  The location of construction is on District-owned property.  See drawings for further information.  The primary objective of the project is to install new, pre-purchased electro-mechanical equipment and other necessary appurtenances at Lift Station No. 2 located on Steele Canyon Road near Arroyo Lindo Dr. in Napa, and perfect ancillary site work as shown in the design plans.

Contract

The Contractor shall possess a Class A license at the time of contract award.  The Engineer's estimate is $50,000.  The mandatory job walk sign in sheet has been posted.