Milton Rd Paving Phase 2 Marshall Ave Drainage Project RDS 19-18

Overview

Project Scope

The project is located on Milton Road in Napa County, CA.  The extents of resurfacing on Milton Road is as shown per plan, beginning approximately 2,700 feet south of Las Amigas Road and continuing south approximately 13,000 feet to the end.

The proposed project will consist but not be limited to placing a pavement reinforcement fabric at specific locations located on the plans, the placement of a 2 inch thick layer of hot mix asphalt over an existing leveling course and restriping the newly paved section of road.

Contractor shall possess a Class A or C-12 License at the time of contract award. The Construction estimate for this project is $874,205. 

Bid Documents

The Notice to Contractors is provided below.  The plans and specifications are now available for viewing.