Steele Canyon Rd MPM 2020 Fire Damage Repair Culvert Replacement, RDS 20-42

Overview

  • Status: Evaluation/Review
  • Contact: Dewey Phan
  • Publish Date: September 11, 2020

Project Scope

The project is located on Steele Canyon Road at Mile Post Marker (MPM) 2.0.  The project site is located approximately 15 miles northeast of the City of Napa, CA.  The proposed project would include repairing the culvert that was damaged during the 2020 LNU Lightning Complex Fire.  

Contract

The Contractor shall possess a Class "A" License at the time of contract award.  The Engineer’s estimate is $120,000. 

Bid Documents

The Plans and Specifications are available in the link below.  The mandatory bidder's list was revised 09-24-20.  Addendum 1 has been added.  The bid opening was September 24, 2020 at 11:30 am.  The project is under Evaluation/Review.

Contractor Location Total Base Bid
Rehak Engineering Auberry, CA $127,042.40
HM Construction Hercules, CA $129,254.00
Suulutaaq, Inc. Suisun City, CA $130,950.00
Maggiora & Ghilotti, Inc. San Rafael, CA $135,135.00
Team Ghilotti Petaluma, CA $138,141.77
Oak  Grove Construction Petaluma, CA $168,488.00
Valentine Corporation San Rafael, CA $190,369.00
E.E. Gilbert Construction Martinez, CA $208,231.41