The Lake Berryessa Resort Improvement District (LBRID) is seeking contractors to purchase and install two stand-by generators for two existing water system pump stations (one at each location) located at different locations of Harness Drive in Pope Valley. Scope of work is includes site work as shown on the conceptual site plans, connection site plans, connection to existing manual transfer switches, and start-up and testing services.
Contract
Each Contractor bidding on the project shall possess a Class "A" or "C-10" license and be registered with the DIR at the time of bid opening. The Engineer's estimate for construction is $90,000.
Bid Documents
The Notice to Contractors and the Plans and Specifications are in the links below. The mandatory sign in sheet has been posted. Addendum 1 and 2 have been posted. The project was awarded by the Board of Supervisors on April 20, 2021 to Summit Signal, Inc. of Willits, CA.