The project is located at: 2210 Napa-Vallejo Highway, Napa, CA.

The scope of this project is to install a 600 amp 277/480 volt, 3 phase, 4 wire temporary power service and all associated equipment in accordance with plans, specifications and PG&E requirements for temporary construction power.

Contractor shall possess a Class C-10 license or Class B with a C-10 subcontractor at the time of contract award. Engineer estimate for this project is $75,000.  The bid opening was  08-19-21 at 11:30 AM.  The project was awarded to St. Francis Electric for their low bid of $91,690.

Bid Documents

The plans and specifications are available for viewing or download. Addendum 1 was added.

ContractorLocationTotal Base Bid
St. Francis ElectricSan Leandro, CA  $91,690.00
Coastal Mtn Electric dba James DayClear Lake, CA$149,999.00
S & H Construction, Inc.Fremont, CA$168,800.00
Pacific Industrial ElectricBrea, CA$190,574.00
MEL ElectricNapa, CA