Overview
- Status: Construction
- Contact: Dewey Phan
- Publish Date: March 11, 2022
Project Scope
The proposed project consists of storm slide repair with lagging/retaining walls and roadway reconstruction caused by the 2017 and 2019 damage in Napa County. The project will commence along: Dry Creek Rd. MPM 6.2, RDS 21-30, Dry Creek Rd. MPM 9.48, RDS 21-39, Dry Creek Rd. MPM 9.75, RDS 21-06 and Diamond Mountain Rd. MPM 1.1, RDS 21-04.
Engineer Estimate: $2,015,000. The Contractor shall possess a Class A License at the time of contract award.
Bid Documents
The bid documents are available for viewing and download in the link below. Addendum 1 was added. Addendum 2 was added with new plansheets on 03/25/22. The bidders list is posted. Addendum 3 has been added. Addendum 4 has been added. The bid opening was 04/07/22 at 11:30 AM, the project was awarded on 04/19/22 to Piazza Construction for their low base bid and add alt. The 3 lowest sublists sheets have been posted. The bid tabulation has been added.