American Canyon Road Rehabilitation, RDS 22-04

Overview

  • Status: Completed
  • Contact: Sydney Diede
  • Publish Date: April 21, 2022

Project Scope

The project extent begins shortly after the intersection of Flosden Road and Newell Drive and continues eastbound to the Napa County limit line into the City of Vallejo and ends at the westbound on and off ramps at Interstate 80.

Engineer Estimate: $350,000.  The Contractor shall possess a Class A or C-12 License at the time of contract award.

Project Map

View a map of the project on the County’s Geographical Information System Map.

Bid Documents

The bid documents are available to view or download. Addendum 1 and 2 have been added.  Bidders list has been added. The bid opening was May 19, 2022 at 11:30 am.  The project was awarded by the Board of Supervisors on June 7, 2022 to Martin Brothers Construction of Sacramento, CA for their low base bid of $498,710.

ContractorTotal Base Bid
Martin Brothers Construction - Sacramento, CA$498,710.00