East Central Paving Project, Phase Three, RDS 21-25C

Overview

  • Status: Complete
  • Contact: Liang Su
  • Publish Date: May 22, 2023

Project Scope

The project is located on Atlas Peak Road from 3681 Atlas Peak Road to End. The proposed project includes but is not limited to asphalt pavement grind outs, moisture compaction of subgrade, asphalt pavement replacement, leveling course, asphalt fibbers, paving fabric, and asphalt pavement, per the project Plans and Specifications. 

The Contractor shall possess a Class “A” or “C-12” license at the time of contract award.  Revised Engineer Estimate: $925,000

Bid Documents

The bid opening was June 15, 2023. The 3 lowest sublists have been posted. The Notice of Intent to Award has been posted. The project was awarded on June 27, 2023 by the Board of Supervisors to Martin Brothers Construction of Sacramento, CA for their low base bid as well as Additive Alternate Number 1 $150,745.80, Number 2 $2,862, and Number 3 $1,200 for a total of $1,305,728. The project is now complete.

ContractorTotal Base Bid
Martin Brothers Construction - Sacramento, CA$1,150,920.00
Argonaut Constructors - Santa Rosa, CA$1,298,430.00
Ghilotti Brothers, Inc. - San Rafael, CA$1,362,520.18
Goodfellow Brothers - Livermore, CA$1,384,230.00
Team Ghilotti, Inc. - Petaluma, CA$1,411,987.00