Bid Number: |
RDS 19-18
|
Bid Title: |
Milton Rd Paving Phase 2/Marshall Ave Drainage Project, RDS 19-18
|
Category: |
Construction, Roads and Public Works |
Status: |
Awarded |
Bid Recipient: |
O.C. Jones & Sons, Inc. of Berkeley, CA |
|
The project is located on Milton Road in Napa County, CA. The proposed project will consist but not be limited to placing a pavement reinforcement fabric at specific locations located on the plans, the placement of a 2 inch thick layer of hot mix asphalt over an existing leveling course and restriping the newly paved section of road.
Contractor shall possess a Class A or C-12 License at the time of contract award. The Construction estimate for this project is $874,205. The project was awarded to O.C. Jones & Sons, Inc. of Berkeley by the Board of Supervisors on July 28, 2020 The 3 contractor sublists have been posted.
Contractor |
Total Lump Sum Bid |
O.C. Jones & Sons, Inc. |
$762,713.00 |
Team Ghilotti |
$775,141.00 |
Martin Brothers |
$928,496.20 |
|
|
5/19/2020 4:00 PM
|
|
NV Register
|
|
6/18/2020 11:30 AM
|
|
[email protected] John Vicencio
|
|
Contractor shall possess a Class A or C-12 License at the time of contract award.
|
|
A mandatory bidder’s list will be required to participate in bidding for this project. The deadline to submit an entry for the list will be May 28, 2020 by 5:00 P.M.; to be placed on the bidder’s list, contact John Vicencio ([email protected]) as noted in Notice to Contractors.
|
|
|
|