The project is located on Atlas Peak Road from 3681 Atlas Peak Road to End. The proposed project includes but is not limited to asphalt pavement grind outs, moisture compaction of subgrade, asphalt pavement replacement, leveling course, asphalt fibbers, paving fabric, and asphalt pavement, per the project Plans and Specifications. Revised Engineer Estimate: $925,000. Addendum 1 has been added, bid opening time has been changed. The bid opening was June 15th, 2023. The 3 lowest sublists have been posted. The Notice of Intent to Award has been posted. The project was awarded by the Board of Supervisors on June 27, 2023 to Martin Brothers of Sacramento, CA for their low base bid as well as Additive Alternate Number 1 $150,745.80, Number 2 $2,862, and Number 3 $1,200 for a total of $1,305,728. Contractor | Total Base Bid |
---|
Martin Brothers Construction - Sacramento, CA | $1,150,920.00 | Argonaut Constructors - Santa Rosa, CA | $1,298,430.00 | Ghilotti Brothers, Inc. - San Rafael, CA | $1,362,520.18 | Goodfellow Brothers - Sacramento, CA | $1,384,230.00 | Team Ghilotti, Inc. - Petaluma, CA | $1,411,987.00 |
|